Location: | Alexandria, Sydney |
Project Manager: | CBD Projects Australia |
Interior Design: | CBD Projects Australia |
M & E: | Systems administration at Panasonic Avionics |
Lighting Services: | JB Electrical |
Total Cost: | $600,000 |
Time to Complete: | 10 weeks |
Total Floor Area: | 300 m2 |
Project Details:
Main reception - troffer lights, curved design detailing featured curved wall with silver embossed wallpaper.
Coffer blue LED lights. Glass presentation shelving.
Workshop - ambilical power & compressed air cabling.
Large breakout area with polished concrete.
Boardroom with whiteboard operable walls.
Open plan & indivual offices. Curved workstations.
Specialist construction requirements:
Installation of New complete Air Conditioning System to whole Tenancy - including carnage of Roof Plant.
Replication of Existing [old location] Comms Room Set-up, Power Distribution, UPS Facilities & reticulated Cabling was required to be completed to the Specific Requirements of the Client 3 wks prior to Occupation for line Testing and Equipment Installation.
"We have engaged CBD Projects and its Principal Mr Robert Bowles for over 8 years. We have always found Robert to be a person of high integrity and our projects have always been completed on time and on budget. The sites are run efficiently with due regard to work safety and co-ordination of the various trades. In our business as Property Investors and Managers having Robert and CBD Projects available has been a valuable asset."